Actions Speak Louder Than Words !
This page is dedicated to the detailed construction of a single story extension of 35 Square Meters in Size.

wbs.westmount@ntlworld.com


All visitors are most welcome.

Regards Richard
WBS @ Westmount
wbs_IMG_7903
wbs_IMG_7909
wbs_IMG_7911
wbs_IMG_7912
wbs_IMG_7913
wbs_IMG_7915
wbs_IMG_7917
wbs_IMG_7934
wbs_IMG_7944
wbs_IMG_7946
wbs_IMG_7947
wbs_IMG_7951
wbs_IMG_7952
wbs_IMG_7954
wbs_IMG_7955
wbs_IMG_7958
wbs_IMG_7959
wbs_IMG_7962
wbs_IMG_7965
wbs_IMG_7968

Work Carried out on the 03/07/2011

Construction of the internal block work to construct the Annex Bathroom and the main house bathroom.

Also the Construction of the front wall and facing bricks to allow the fitment of the main front window.




As The Main Summer shutdown ( JCB Fixed Holidays )  creeps ever closer, the main focus is towards all outstanding jobs prior plastering.

I needed to get all internal wall construction done to allow me to install the electrical Power Sockets, Light Switches and Wall Lights points etc into the block work.

This is in preparation for the electrician to wire up and supply the relevant Part "
P" electrical certificate for the buildings inspector.


So how did it all go?

The day started at 7:30 and i had in my plan to build up the front wall block and  facing bricks the internal block work walls.

This consisted of……

250 Blocks
150 Facing Bricks
2 Door Lintels’

Did we finish it all? 
Yes


We finished building at about 4:30pm and I continued until about 8:30pm cleaning up tools and floor etc

The only small error that was made is that the top row of facing bricks on the front wall was not up to my normal picky standard of levelness and as the plan was to sit a large window across this row of bricks i was concerned that it would become even more obvious.


Now i did not lay these bricks but also due to being busy myself helping with the blocks and mixing i failed to check the work of bricklayer.

Never mind in my normal way i just fetched off the top row and plan to relay them next week one evening after work.

All in all the day went excellent and it’s another large job closed off the “Work to Project List”.
DONE

Below as usual some pictures of the process





Updated 18/08/2011

This is now not to lay the top row of bricks on the front wall and the rectification process.

The Hall of Shame !
wbs_IMG_7925
wbs_IMG_7926
wbs_IMG_7928
wbs_IMG_7931
wbs_IMG_7933
wbs_IMG_7935
wbs_IMG_7936
wbs_IMG_7939

Updated 18/08/2011

Top Row of Bricks removed and relpaced level and in line.
wbs_IMG_7969
wbs_IMG_7972
wbs_IMG_7974
wbs_IMG_8002