This page is dedicated to the detailed construction of a single story extension of 35 Square Meters in Size.
wbs.westmount@ntlworld.com
All visitors are most welcome.
Regards Richard
WBS @ Westmount
Work carried out during the main JCB summer shutdown 25/06/2011
Pre Plastering Jobs Required.
This is a record of the Jobs that needed to be done prior to the Plasterers coming on the 08/08/2011.
The main jobs included
The channelling out of the walls for the central heating radiator pipe work.
Installing all the electrical switches and plug sockets for the Electrician.
Battening vaulted ceilings in preparation for the Plasterboard.
The main plaster boarding of the ceiling and the one wall.
Pass Soil Pipe through roof and arrange for roofer to felt around to make watertight.
Insulate radiator pipe work in walls and in wooden joists.
We screwed in over 2500 Plasterboard screws so far to date with probably another 500 to go in the main bathroom vaulted ceiling.